A budget is only useful if you compare it with what really happened, and then do something about the difference. That comparison is called variance analysis. Most businesses do the sums; fewer turn them into decisions.

The calculation

For each line:

  • Variance = actual minus budget
  • Variance % = variance divided by budget

A revenue line that came in at £90,000 against a budget of £100,000 has a variance of minus £10,000, or minus 10%.

Sign conventions cause the most confusion, so agree one and keep it:

  • Favourable means the result is better for profit: revenue above budget, or costs below it.
  • Adverse means worse for profit: revenue below budget, or costs above it.

Label every variance favourable or adverse rather than relying on a plus or minus sign, because a positive number is good for revenue and bad for costs.

Which variances matter

Not every variance deserves a paragraph. A pack with fifty explained variances is as unreadable as one with none. Use two filters together:

  1. Size in pounds. A line that is 30% over budget but only £400 is noise.
  2. Size in percentage. A £10,000 variance on a £2m line is rounding; on a £50,000 line it is a problem.

Pick thresholds that suit your business, for example anything over both £5,000 and 10%, and explain only those.

Look beyond the month

A single month can mislead. Always show:

  • Year to date, because it smooths timing.
  • The forecast for the full year, because the question that matters is where you will land.

A favourable month can hide a worsening trend, and an adverse one can simply be an invoice that landed a week late.

Separate the causes

For each material variance, ask which of these it is:

  • Timing. The money will arrive or leave next month. No action, but update the forecast.
  • Volume. You sold or bought more or less than planned.
  • Price or rate. The same activity cost or earned a different amount.
  • Mix. The total looks right, but the make-up has shifted towards lower-margin work.
  • Error or reclassification. The budget and the actuals were coded differently. This is more common than people expect, and it produces variances that look real. If a ratio disagrees with your own model, check how each side is mapped before you act on it.

The cause decides the action, so the commentary should name it.

Write commentary that leads somewhere

Weak: "Overheads were £12,000 over budget."

Better: "Overheads were £12,000 over budget, of which £9,000 is a software renewal paid in October rather than January. The underlying overspend is £3,000, mainly recruitment fees. We expect the full year to land £4,000 over."

Say what happened, why, and what it means for the year.

Make it routine

Variance analysis works when it is part of the monthly close, not a separate project. It needs the budget loaded in the same structure as the actuals, so each line compares like with like.